Elivia Homes, along with West Sussex CC and all involved service companies are working together, sharing road space and helping each other out to insure disruption to a minimum and speeding up the process of completing necessary works on the highway.
7-7-2025 - I&G (gas) commencing diversion works for a period of up to six weeks. Within this period, we will be also installing part of the SSE electric cable within the same trench.
- Approx. 100m from Shripney lane moving north up Shripney road.
- I&G to complete road reinstatement upon completion of works.
- 11-8-2025 - Our Groundworks team BCT will then take over the traffic management and continue works for another four weeks. Within this period the remainder of the SSE electric cable will be laid.
- Approx 120m north moving up Shripney road.
- BCT to complete reinstatement works upon completion.
Joe Totten
Contracts Manager
Elivia Homes
07377 149708
joseph.totten@eliviahomes.co.uk